|

Prince2 Revision Keypoints
|
Project Mandate
Triggers
SU Starting up a Project
Identifies
the Project Executive
content
varies with the project type and size but could include:
Authority
and Objectives
Scope
and constraints
Quality
expectations
Identifying
a Business Case
Identifying
the Project Executive and Project Manager
Customer,
User and ALL interested parties
|
SU Starting up a Project, Overview
Use
the Project Mandate to:
·
confirm
that the project is worthwhile
·
define
responsibilities and roles
·
create
the Initiation Stage Plan to enter IP Initiating a Project
·
provide
information for the Project Brief
·
establish
the Project Approach
·
design
and appoint the Project Management Team
·
create
the Stage Plan
·
help
in setting up the Risk Log
This
should be a short, inexpensive process
|
|
SU1 Appointing a Project Board Executive and a Project Manager
·
identify
candidates for the Project Manager and Executive positions
·
verify
roles with candidates and Programme Management
·
appoint
the Project Executive and Project Manager
|
SU2 Designing a Project Management Team
·
produce
Job Description(s)
·
consider
the project size +areas of involvement
·
identify
required skills and responsibilities
|
|
SU3 Appointing a Project Management Team
·
Use
Job Description(s) to ensure everyone has a clear understanding of:
o
what
they are responsible for
o
who
they report to
·
acceptance
of roles by the Team Manager
·
file
the signed job descriptions
|
SU4 Preparing a Project Brief
·
use
the Project Mandate to produce:
o
Risk
Log
o
Project
Brief
o
IP1
Planning Quality
verify
Business Case
|
|
SU5 Defining Project Approach
·
produced
in-house
·
produced
by 3rd party
·
developed
in house
·
an
'off the shelf' product
|
SU6 Planning an Initiation Stage
•
Create Stage Plan for DP1 Authorising Initiation
•
Update Risk Log
|
|
Project Brief
basically
a mini PID - used as the basis for the PID upon approval
includes:
*
Project definition (scope, objectives, constraints, deliverables)
*
Business Case outline - reason for this solution
*
Quality expectations * Acceptance Criteria * Risks
When
part of a Programme it supplies the Project Brief
Developed
from the Project Mandate be sure that it reflects the Project Mandate
|
IP Initiating a Project
· Forms a contract
between the Project Manager and the Project Board cementing the understanding
of what will be delivered, how, by when and by whom
· First step to helping
the Project Board to take ownership of the project
· Defines how quality
will be achieved
· Creates a plan to
react to a Customer's quality expectations
At
each relevant point consider the Programme as a whole
|
|
IP1 Planning Quality
Once
authorised by DP1 Authorising Initiation use the following documents:
·
Project
Brief
·
Project
Approach
•
To produce the Project Quality Plan that should outline:
·
Responsibilities
·
Criteria
·
Sign
off sequence
·
Configuration
Management Plan
|
IP2 Plan a Project
·
Produce
the Project Plan by using the Project Approach, Project Brief and Project
Quality Plan, in particular:
·
Identify
the project's product(s)
·
Assess
counter measures to all risks
·
Estimate
the:
o
Effort,
o
Time
and
o
Costs
|
|
IP3 Refine Business Case and Risks
·
This
process's purpose is primarily to create a Business Case that can be used in
the Project Initiation Document.
·
The
Business Case is based on the Project Brief's outline Business Case
·
Refine
question of "Why?" the project is being done
·
Evaluate
Business risks
·
Ensure
benefit realisation by User and Customer
·
Discuss
issues with Project Board before presenting the Project Initiation Document
·
Update
Risk Log
·
Identify
negatives and positives
·
Update
Project Plan and, if necessary, revise Project Plan
|
IP4 Setup Project Controls
·
Produce
the Communications Plan and Project Controls (will form part of the Project
Initiation Document)
·
Estimate
and evaluate levels of:
o
Risk
and complexity
o
Reporting
required
·
Identify:
o
Stakeholders
o
Monitoring
mechanisms
o
Resources
required
|
|
IP5 Setup Project Files
· Produce the Quality
Log, Lessons Learned Report, Issue Log
· Efficiently store and
retrieve the projects documents and products
· Meet appropriate
requirements for:
· The project's scale,
risk and complexity
· Usability, accuracy,
and timely retrieval
· Auditing requirements
(i.e. Lessons Learned Report)
|
IP6 Assembling a PID
·
Produce
a Project Initiation Document
·
Answer
the questions What? Why? Who? How ? When?
·
Provide
an information base for all involved with the project
·
Forward
the PID to DP2 Authorising a Project
|
|
DP Directing a Project
·
Carried
out by the Project Board Directing a Project is to:
·
Authorise
the commitment of resources to a project
·
Ensure
Risks are managed
·
Ensure
objectives are being met, as laid out in the Business Case
·
Make
decisions required by the Project Manager regarding the project
·
Direct,
if necessary, a project into premature closure
·
Ensure
a clean, orderly closure to a project
·
Responsibility
lies with the Project Board
Directing
a Project sub-processes are:
DP1
Authorising Initiation
DP2
Authorising a Project
DP3
Authorising a Stage or Exception Plan
DP4
Giving ad hoc Direction
DP5
Confirming Project Closure
|
DP1 Authorising Initiation
·
Ratify
the Project Brief and Business Case
·
Approve
the plan to produce the Project Initiation Document Commit resources
·
This
process may be shortened when the Project Brief has been provided by the
Programme
·
Use
the following documents to enable the Project Board to give approval:
o
Business
Case
o
Draft
Initiation Stage Plan
o
Risk
Log
o
Job
Description(s)
o
Project
Approach
o
Project
Brief
|
|
DP2 Authorising a Project
·
Give
final approval to the Project Initiation Document
·
This
stage is combined with DP3 Authorising a Stage or Exception Plan meaning the
Project Initiation Document and Stage Plan is approved together
·
Once
accepted the Project Initiation Document should be frozen and stored with the
Configuration Librarian
·
With
the acceptance of the PID comes the Authorisation to Proceed
·
The
draft PID comes from IP6 Assembling a PID
·
Authorisation
to proceed then passes to CS1 Authorising a Work Package
|
DP3 Authorising a Stage or Exception Plan
·
An
Exception Plan is a Stage Plan under "exceptional circumstances"
and are treated in the same way
·
Once
approved an Exception Plan becomes a Stage Plan
·
Information
required:
o
Current
status of the stage or project
o
Forecasts
o
Assess
end dates and risk situation
·
Assess
the Business Case
·
Combined
with DP2 Authorising a Project when seeking Project Initiation Doc
·
Can
precede SB5 Reporting Stage End & SB6 Producing an Exception Plan approved
Stage Plan or Exception Plan
|
|
DP4 Giving ad hoc Direction
·
Outlines
the advice and direction to the Project Manager by the Project Board
·
Things
to discuss include:
o
Project
Board changes
o
Risk
o
Request
for Change
o
Statement
of concern
o
Off-Specification
requests
o
Project
Issues
·
This
can be useful at any point in the project
·
Highlight
Reports from the Project Manager keeps the Project Board formally up-to-date
|
DP5 Confirming Project Closure
·
Actioned
once either the last stage is completed
·
Ensures
a clean, orderly closure to a project
·
Ensure
an organised hand-over to the Customer
·
Establish
a method for evaluating the product
·
Publish
and distribute plans for the Post Project Review
·
Ensure
there is Customer approval
·
Hand-over
configuration management to ensure on-going control
·
Project
Closure Notification
·
Often
this process is resulted from CS2 Assessing Progress or CS3 Capturing Project
Issues and leads to a End Project Report and Post Project Review
|
|
CS Controlling a Stage
Outlines
the day-to-day responsibilities of the Project Manager including:
o
Allocating work o Checking progress o Ensuring quality o Managing
changes
o
Monitoring risks o Reporting progress o Watching deviations
This
is an event driven process often triggered in an ad hoc manner
|
CS1 Authorising a Work Package
· Enables Project
Manager control over commencing and continuing work
· Involve the Team
Manager/Member with the work package creation (including quality
expectations)
· Integrated with Work
Package hand-over in MP 1 Accepting a Work Package
|
|
CS2 Assessing Progress
·
The
Project Manager assesses progress by looking at Checkpoint Reports, Work
Packages, and the Quality Log
·
Team
Managers use progress and quality information to create a Checkpoint Report
for the Project Manager
·
Assess
time and resources
Update
Stage Plan
|
CS3 Capturing Project Issues
·
Usually
ad hoc - Project Issue are dealt with as they arise
·
Update
and categorise Project Issues in the Issue Log
Uses
Change Control Approach
|
|
CS4
Examining Project Issues
·
Examine
as listed in the Issue Log and identified in CS3 Capturing Project Issues
·
Ensure
the following information that effects the project is gathered including:
o
Costs
o
Time-scales
o
Benefit
achievement and/or value
o
Risks
·
Update
the Risk Log
·
"examining
project issues" should be performed on a regular basis
· Used to update the
Risk Log and Issue Log
|
CS5 Reviewing Stage Status
· This stage is central
to "Controlling a Stage" sub processes
· By checking Tolerance
and the status it is the decision point to either:
o
Issue
further Work Packages
o
Issue
plan modifications to existing Product Descriptions
· If the stage is within
tolerances and meets the Stage Plan requirements proceed to CS6 Reporting
Highlights and CS1 Authorising a Work Package
· If the stage is
outside tolerances proceed to CS8 Escalating Project Issues
Configuration
Management should show the status of a stage relative to the original Stage
Plan
|
|
CS6
Reporting Highlights
·
Used
to meet Communications Plan requirements
·
Create
Highlight Report for the Project Board
·
Suggested
length no more than 1-2 pages
|
CS7 Taking Corrective Action
·
Resolve
any deviations from the Stage Plan
·
Often
incorporated with DP4 Giving ad hoc Direction
·
Identify
the cause and effect of the deviation
Update
Stage Plan
|
|
CS8 Escalating Project Issues
·
Provide
recommendations and options to the Project Board
·
Perform
impact analysis on both The Customer's and User's Business Case
·
Possible
causes:
o Corrective action forcing the
Stage Plan beyond Tolerance
o Inaccurate estimations
Results
in the creation of an Exception Report
|
CS9 Receiving Completed Work Package
·
To
ensure the completed Work Package matches the Product Description
·
Check
approvals as laid out in the Acceptance Criteria
·
The
Work Package is set as a Baseline and given to Configuration Management
|
|
MP Managing Product Delivery
•
Responsibility lies with the Team Manager
•
Encompasses the following responsibilities of the Team Manager, these are to:
o Ensure work is authorised and
agreed
o Accept and check Work Package
o Create a Team Plan
o Ensure work progress and
forecasts are assessed
•
Basic objectives:
o Agree the Work Package with
the Project Manager
o Get the work done
o Hand back the completed work
•
Managing Product Delivery includes the following processes:
o MP1 Accepting a Work Package
o MP2 Executing a Work Package
o MP3 Delivering a Work Package
|
MP1 Accepting a Work Package
·
The
Team Manager should produce a Team Plan that shows how the Work Package can
be completed within the constraints
·
The
Team Manager should:
o Understand reporting
requirements
o Agree tolerance margins for
the work package
o Understand what is to be
delivered
o Accept the constraints (time,
cost etc.)
o Agree on the reasonable
requirements for:
Reporting (including
to whom)
Frequency and detail
of Checkpoint Reports (defined in the Stage Plan)
Quality (as mentioned
in the Product Description)
Procedures (such as
updating the Risk Log, Quality Log and
Risk analysis,
planning and resources
|
|
MP2 Executing a Work Package
•
The Team Manager is responsible for:
o Determining the status of the
Work Package
o Controlling risks/and effort
o Evaluating remaining effort
required
o Creating Status and Progress
Reports
o Ensuring quality checks are
carried out
o Advising the Project Manager
of problems
•
It is possible that the organisation carrying out this stage does not use
PRINCE2
|
MP3 Delivering a Work Package
•
During this process the Team Manager has 3 main objectives:
o Obtain quality and acceptance
sign-off
o Hand over the products (to
Configuration Management)
o Advise the Project Manager
upon completion
· It is the
responsibility of the Team Manager to ensure that the Work Package is handed
over correctly
· The delivery is
controlled by Configuration Management
|
SB Managing Stage Boundaries
•
Responsibility of the Project Manager
•
Basic process:
o
Gather results
o
Plan next stage
o
Update Project Plan and Risk Log if required o Seek stage approval
•
Key points:
o
Ensure that any changes to the Project Plan still support the Business Case
o
Check the Project Approach and Configuration Management for improvements
o
Options at the end of each stage include redirecting the project or stopping
the project
|
SB Managing Stage Boundaries (cont)
•
Key objectives:
o
Assure the Project Board that products have been completed
o
Provide information about the on going viability of the project
o
Obtain next stage authorisation and Tolerances (cost and time)
o
Update Lessons Learned Log
•
Sub processes include:
o
SB1 Planning a Stage o SB2 Updating a Project Plan
o
SB3 Updating a Project Business Case o SB4 Updating the Risk Log
o
SB5 Reporting Stage End o SB6 Producing an Exception
Plan
|
|
SB1 Planning a Stage
•
Prepare the next Stage Plan from the Project Plan
•
Be sure to include management products (ie PRINCE2 reports and plans)
•
Consult with Project Assurance to check expectations are being met
•
Review the Project Management Team structure for possible changes
|
SB2 Updating a Project Plan
•
Update from Stage Plan or Exception Plan namely the:
o Project Quality Plan
o Project Approach
|
|
SB3 Updating a Project Business Case
•
This is an essential process that maintains the project's viability
•
Within the process revise costs, timings and benefits
•
Update Risk Log and Issue Log
•
Changes to the Business Case must be approved by the Project Board
•
Changes can be for the better or worse
|
SB4 Updating the Risk Log
•
Analysed and updated when a risk has increased, decreased, occured or stayed
the same.
•
Each Risk should have an "owner"
|
|
SB5 Reporting Stage End
•
Occurs when a stage is nearing an end or an Exception Plan is created
•
Present to the Project Board with the original Stage Plan and a summary of
the Issue Log the execution of this stage should have been forecast during CS
|
SB6 Producing an Exception Plan
•
Undertaken once an Exception Report has been presented to the Project Board
and approval has been given to produce an Exception Plan
•
Is due to a stage or the project exceeding Tolerances
•
The execution of this stage should have been forecast during CS Controlling a
Stage
|
|
CP Closing a Project
· Produces an End
Project Report and Lessons Learned Report
· Confirms operational
and maintenance acceptance of products
· Ensures a clear end to
a project
· Required because all
projects are (and should be) finite
· Majority of the work
is in gaining Project Board approval
· Closing a Project
processes are done in parallel - they do not depend on each other
· Without a clear
project closure there is a tendency to drift into operational management
· Provides an
opportunity to take stock of achievements
· Sub processes in CP
Closing a Project are:
o
CP1 Decommissioning a Project
o
CP2 Identifying Follow-on Actions
o
CP3 Project Evaluation Review
|
CP1 Decommissioning a Project
·
The
Project Manager is responsible for this process
·
Both
the Customer and Supplier should be in agreement that the project has come to
an end
·
Notify
everyone involved about the project closure (Project Closure Notification)
·
Products
should be officially handed over
·
Ensure
maintenance is in place
·
Create
Status Account (using Configuration Management)
|
|
CP2 Identifying Follow-on Actions
·
The
Project Manager is responsible
·
Document
Follow-on Action Recommendations
·
Recommend
date for Post Project Review (evaluate the benefits as outlined in the
Business Case)
·
Produce
plan for Post Project Review
|
CP3 Project Evaluation Review
•
Assess the project's
o Results
o Quality of management
o Quality of Risks and quality
management
•
Identify the lessons learned from the Lessons Learned Report
|
|
PL Planning
·
As
PRINCE2 is a product based methodology 'what' is to be produced is defined
first along with its product description
·
Ensure
that the plan includes time and resources for project and quality management
·
The
principles are What (e.g. Description and quality), Why and How (e.g. By
whom, what sequence)
·
Basic
steps (once the what, why and how have been answered):
o When, by whom
o Amount of effort that will be
required o Determine how long it will take
o Determine quality control
o Calculate costs
o Decide on budget
o Assess risks
o Determine control points
|
PL1 Designing a Plan
·
The
detail level of the plan is determined by the planning approach
·
Identify
the maximum length of time and how to measure the quality of the product
·
To
achieve required estimations the following my be employed:
o Computer tools
o Experienced planners in this
area
o Either top-down or bottom-up
estimation
o Discussions with others
·
Allowances
to consider:
o Change Budget
o Contingency Plans
·
Responsibility
lies with the Project Board
|
|
PL2 Defining and Analysing Products
·
Uses
Product Based Planning
·
Outline
the management of all (Specialist and Management) products and their quality
requirements
·
Ensure
all the product specifications are approved
·
Sequence
these products in order of their creation
|
PL3 Identifying Activities and Dependencies
•
Completes the Product Flow Diagram
•
Identify activities required by the project from external contractors
•
Estimate interdependencies that may exist between these activities
•
Deal with any dependencies by ensuring they are sequenced appropriately
•
Resource availability is dealt with in PL5 Scheduling
|
|
PL4 Estimating
•
The two major steps in estimating are:
o Identify resources required
o Estimate effort required for
each activity
•
Identify resources and time required for each activity. Be sure to include:
o Specific skills
o Degree of confidence and margin
of error
o Assumptions made
o Level of product and activity
understanding
|
PL5 Scheduling
•
Will be changed and updated to ensure agreement between all parties
•
Steps are:
1.
Create planning network
2.
Assess resource availability
3.
Produce draft schedule and assign responsibilities
4.
Reassess the level of resource usage after reassigning activities
5.
Confirm control points with the Project Board
6.
Calculate resources and costs to produce the plan budget
|
|
PL6 Analysing Risks
•
Ensure the cost of avoiding the risk does not exceed the cost of risk itself
•
If there is something not under the control of the Project Manager there IS a
risk
•
Evaluate each resource in the project for risk
|
PL7 Completing a Plan
·
Project
descriptions, risk analysis, the schedule and estimations should be
consolidated and presented to the Project Board
·
Product
Checklist should have start and end dates
·
Tolerance
Margins should be set by the Project Board
·
A
GANTT Chart or bar diagram of the Schedule should be included
·
Once
approved the Project Board 'freezes' the plan, thereby setting a Baseline
·
Project
Manager is responsible
|
|
Component 1, Business Case
The
business case is the description for the reasons of the project and the
justification. Covers the entire scope of change
The
most important set of info for the project.
What
should it contain?
•
Reasons • Options • Benefits Expected • Risks
•
Cost and Timescale • Investment appraisal • Evaluation
Developing
the business case
· Executive is the owner
· Project mandate is
used to develop the information required for the business case.
· During project start
up the BC is updated to provide more detailed information on the benefits,
risks, options, and costs. PP gives a clearer view of this.
· Formal approval of the
business case is required by the executive
· During each stage of
the project the BC is reviewed
· BC provides all
stakeholders with basic info on the project. CP covers when BC info is
communicated to stakeholders.
· At project close the
BC confirms project has delivered
At
project close the BC is the basis for the post project review plan.
|
|
Component 2, Organisation
Four layers
•
Corporate or programme management
•
Direction (PB)
•
Day to day management (PM)
•
Team management and product delivery ( TM)
Three project interests
•
Business - Should meet a business need
•
User - use, achieve objective, benefits, impact • Supplier - skill
supplier
|
Senior Supplier
•
Needs to achieve results required by senior user
•
Within timescale and costs
Project Assurance (Optional)
•
All appointments independent of the PM and made by the PB
Project Support (Optional)
PM
may need admin help
Role
can include configuration librarian
|
|
Organisation, Project Executive
ultimately
responsible for the project supported in the Project Board by the Senior User
and Senior Supplier owns the Business Case balances the demands of the User,
Supplier and Business responsibilities include:
·
approve
Project Board
·
| |